Standard Coordinators Report

2006 - May 16,2006



The Standards Coordinator, Jeffrey Gilbert, met with the Chairs of the Working Groups writing and revising standards documents at a session beginning at 8:00 AM on May 16, 2006, in the King Street 4 room of the Desmond Hotel, Albany, NY.

Yvette Ho Sang, Manager, Standards Publishing Programs,  and Michelle Turner, Associate Project Editor, answered questions concerning standards development and publication.  

The status of selected PARs, Standards and Guides, were reviewed at the meeting. The status of the PARs is summarized below. The actions to be taken for keeping up-to-date the approval of the PARs and for keeping live the Standards and Guides are identified. A summary of the specific approvals received, since the January 2006meeting of the PSRC, are identified as well.

Information concerning the Standards Association (SA), Board of Governors, Committees of SA, the Development of standards, Recommended Practices and Guides and related issues is available on the following web site.

http://standards.ieee.org/

Some of the other web sites for obtaining useful information are as follows.

 

                                                                                                                                               

Information on

Web site address

Update your information with SA

 

http://standards.ieee.org/resources/development/

myBallot Voter presentation

http://standards.ieee.org/db/balloting/myballotdemo.ppt

myBallot Chair presentation

http://standards.ieee.org/db/balloting/myballotchairdemo.ppt

PAR application, extension and other forms

http://www.standards.ieee.org/guides/par/

 

 

Submitting a PAR

http://standards.ieee.org/guides/par/ePARform.html

PAR Extension

http://standards.ieee.org/guides/par/extension.rtf

Style manual

http://www.standards.ieee.org/guides/style/2000Style.pdf

Template

http://www.standards.ieee.org/resources/spasystem/index.html

Up-load drafts for balloting

http://standards.ieee.org/eprocess/upload_balloting_file/

 

Request for invitation to ballot

http://standards.ieee.org/resources/development/

Follow: Balloting the Draft ® Ballot Invitation ® Requesting a Ballot Invitation

Join a balloting pool

 

Submit request for initiating balloting

http://standards.ieee.org/resources/development/

Follow: Balloting the Draft ® Sponsor Ballot ® Requesting Initiation of a Ballot

Submit request for recirculation ballot

http://standards.ieee.org/resources/development/

Follow: Balloting the Draft ® Sponsor Ballot ® Requesting Initiation of a Ballot ® Recirculation ballot

Status of standards etc

Http://www.standards.ieee.org/db/status/status.txt

NesCom activities

http://www.standards.ieee.org/board/nes/

RevCom activities

http://www.standards.ieee.org/board/rev/

SA Operations Manual

http://standards.ieee.org/sa/sa-om-toc.htm

 

SA Bylaws

http://standards.ieee.org/guides/bylaws/index.htm

SB Operations Manual

http://standards.ieee.org/guides/opman/index.html

SB Bylaws

http://standards.ieee.org/guides/bylaws/index.html




Some important Information

The IEEE-SA Standards Board Bylaws and the IEEE-SA Standards Board Operations Manual. The text of the changes made to these documents in 2005 can be found at http://standards.ieee.org/board/pro/2005changes.pdf

 

The IEEE Standards Association (IEEE-SA) Standards Board has launched a new online Project Authorization Request (PAR) Form.  The upgraded online PAR Form (http://development.standards.ieee.org/cgi-bin/NesCOM/myP_par?start)  leads you step-by-step through the PAR process.

 


Standards Coordination Effort

PARs applied for by all Committees of the Power Engineering Society (PES) are circulated among the Standards Coordinators of the PES Committees. Every PAR approved by the Standards Board is posted on the SA Web site at the following address.

http://standards.ieee.org/board/nes/approved.html

The following PAR's were approved in the March 2006 IEEE-SA Standards Board meeting may be of interest to PSRC attendees.

PC37.2 - Standard Electrical Power System Device Function Numbers and Contact Designations.  The PAR can be found at http://standards.ieee.org/board/nes/projects/C37-2.pdf.  The PSRC has formed working group I14 to provide input.

P1775 - Powerline Communication Equipment - Electromagnetic Compatibility (EMC) Requirements - Testing and Measurement Methods.  The PAR can be found at  http://standards.ieee.org/board/nes/projects/P1775.pdf

P1613-2003/Cor 1 - Standard Environmental and Testing Requirements for Communications Networking Devices in Electric Power Substations - Corrigendum 1.  The PAR can be found at  http://standards.ieee.org/board/nes/projects/1613-2003-Cor-1.pdf.

 

P1692 - Guide for the Protection of Communication Installations from Lightning Effects.  The PAR can be found at http://standards.ieee.org/board/nes/projects/1692.pdf

 

P1689 - Trial Use Standard for Cyber Security of Serial SCADA Links and IED Remote Access .  The PAR can be found at http://standards.ieee.org/board/nes/projects/1689.pdf.

If you are interested in the development work planned in a PAR, contact the Chair of the Working Group that is developing the document and sign up for participating in the activity of that Working Group.


Standards Activities Since The September 2005 Meeting

The status of the standards activities, which have taken place since the September, 2005, meeting of the PSRC, are as follows.

1.           Standards Published

C37.90

Standard for Relays and Relay Systems Associated with Electric Power Apparatus

C37.118

Standard for Synchrophasors for Power Systems

 

C37.119

Guide for Breaker Failure Protection

C57.13.3

Guide for Grounding of Instrument Transformer Secondary Circuits and Cases (after resolving negative ballots)

2.              Standards waiting to be Published

 None

 

3.              Standards reaffirmed

None

 

4.              Standards withdrawn

None

 

5.              Standards approved

None

 

6.           Standards submitted for approval

None

 

7.           Standards to be submitted for approval

None

 

8.            Submitted for Balloting/ Recirculation

   C37.99

IEEE Guide for the Protection of Shunt Capacitor Banks

PC37.110

Guide for the Applications of Current Transformers Used for Protective Relaying Purposes

 

PC37.117

Guide for the Application of Protective Relays Used for Abnormal Frequency Load Shedding and Restoration

PC37.230

Guide for Protective Relay Applications to Distribution Lines

9.       Standards Balloted

PC37.230

Guide for Protective Relay Applications to Distribution Lines

10.       Standards Re-circulated

    C37.99

IEEE Guide for the Protection of Shunt Capacitor Banks

PC37.110

Guide for the Applications of Current Transformers Used for Protective Relaying Purposes

11.       Standards to be Re-circulated

PC37.102

Guide for AC Generator Protection                                                       

PC37.105

Standard for Qualifying Class 1E Protective Relays and Auxiliaries for Nuclear Power Generating Stations

PC37.109

Guide for the Protection of Shunt Reactors

12.       Standards due for 5 year review/to be submitted for Re-affirmation

C37.90.3

IEEE Standard Electrostatic Discharge Tests for Protective Relays

 

C37.96

IEEE Guide for AC Motor Protection

 

C37.98

IEEE Standard Seismic Testing of Relays

C37.99

IEEE Guide for the Protection of Shunt Capacitor Banks

 

C37.101

IEEE Guide for Generator Ground Protection

 

C37.102

IEEE Guide for AC Generator Protection

 

C37.109

Guide for the Protection of Shunt Reactors

C37.110

IEEE Guide for the Application of Current Transformers Used for Protective Relaying Purposes

C37.112

IEEE Standard Inverse-Time Characteristic Equations for Overcurrent Relays

 C57.13.1

Guide for Field Testing of Relaying Current Transformers

 

 

 

 The PARs approved since January, 2006, submitted, and the PARs for which extension has been applied are as follows.  PARs, which will expire in 2006, are also listed.  Applications for extending the lives of these par's must be submitted before the 16 October 2006 submittal deadline (for the December 2006 standards board meeting.

 

13.        New PARs applied for

None

 

14.        New PARs approved

None

 

15.        PAR Extensions applied for

None

 

16.        PAR Extensions approved

None

 

17.        Modified PAR approve

None

18.        Modified PAR Submitted

None

19.        PARs Wthdrawn

PC37.94a

Standard for N Times 64 Kilobit Per Second Optical Fiber Interfaces Between Teleprotection and Multiplexer Equipment - Amendment 1: Addition of Alternate Interface Using Single-mode Fiber

20.        PARs expiring at the end of 2006

PC37. 98

Standard  Seismic Testing of Relays

 

 

PC37.101                     

Guide for Generator Ground Protection

 

PC37.102

Guide for AC Generator Protection

 

PC57.109

Guide for the Protection of Shunt Reactors

 

PC37.110

Guide for the Applications of Current Transformers Used for Protective Relaying Purposes

 

PC37.116

Guide For Protective Relay Application To Transmission-Line Series Capacitor Banks

 

PC37.117

Guide for the Application of Protective Relays Used for Abnormal Frequency Load Shedding and Restoration

 

PC37.230

Guide for Protective Relay Applications to Distribution Lines

 

PC37.231

Recommended Practice for Microprocessor-based Protection Equipment Firmware Control

 

PC57.13.1

Guide for Field Testing of Relaying Current Transformers

 

 

 

 

SUBMITTAL DEADLINES & STANDARDS BOARD MEETING SCHEDULE

PAR/Standard Submittal Deadline

Standards Board Meeting

April 28, 2006

June 6, 2006

August 4, 2006

September 14, 2006

October 16, 2006

December 1, 2006

 

For further information download the report and spreadsheet from this site

or contact: Jeffrey G. Giilbert - PSRC Standards Coordinator at

jggilbert@ieee.org/font>