The Standards Coordinator, Jeffrey Gilbert, met with the Chairs of the
Working Groups writing and revising standards documents at a session beginning
at
Jennie Steinhagen, Program Manager, Document
Development IEEE Standards Activities, and Lisa Perry spoke about the IEEE-SA
Word template and answered questions in an afternoon session held at
The status of PARs
is summarized below. The actions to be taken for keeping PAR approvals
up-to-date and for keeping Standards and Guides alive are identified. A summary
of the specific approvals received, since the January, 2008 meeting of the
PSRC, is identified as well.
Information concerning the Standards Association (SA), Board of Governors, Committees of SA, and development of standards, recommended practices and guides and related issues is available on the following web site.
http://standards.ieee.org/
Important
Information
A new set of
Patent Slides for use at all Standards Development meetings. The slides are available at:
PPT version:
http://standards.ieee.org/board/pat/pat-slideset.ppt
PDF version:
http://standards.ieee.org/board/pat/pat-slideset.pdf
Standards Coordination Effort
PARs applied for by all Committees of the Power Engineering
Society (PES) are listed in the NESCOM meeting minutes. The March 26,2008 meeting minutes included a
PAR request submitted by the IEEE PES Transmission and Distribution Committee:
P1782
“Guide for Collecting, Categorizing and Utilization of Information
Related to Electric Power Distribution Interruption Events.”
This PAR request was tabled
to a future meeting due to a lack of response.
If you are interested in this development work, contact the Chairman or
Secretary of the Transmission and Distribution Committee.
Standards Activities Since The January, 2008 Meeting
The status of the standards activities, which have taken place since the May, 2007, meeting of the PSRC, are as follows.
1. Standards Published
C37.230 Guide
for Protective Relay Applications to Distribution Lines
C37.235 Guide for the Application of Rogowski Coils used for Protective Relaying
2. Standards waiting to be Published
C37.91 IEEE Guide for Protective Relay Applications to Power Transformers
C37.110 IEEE Guide for
the Application of Current Transformers Used for Protective Relaying Purposes
3. Standards Reaffirmed
C37.94 IEEE
Standard for N Times 64 Kilobit Per Second Optical
Fiber Interfaces Between Teleprotection
and
Multiplexer Equipment
C37.104 IEEE Guide for Automatic Reclosing of Line Circuit Breakers for AC Distribution and Transmission Lines
4. Standards submitted for reaffirmation
C37.94 IEEE
Standard for N Times 64 Kilobit Per Second Optical Fiber Interfaces Between Teleprotection
and Multiplexer Equipment
C37.104 IEEE Guide for Automatic Reclosing of Line Circuit Breakers for AC Distribution and Transmission Lines
5. Standards approved
C37.91 IEEE Guide for Protective Relay Applications to Power Transformers
6. Standards submitted for approval
None
7. Standards to be
submitted for approval
None
8. Submitted for Balloting/ Recirculation
C37.94
IEEE Standard for N Times 64 Kilobit Per Second Optical Fiber Interfaces
Between Teleprotection
and Multiplexer Equipment
9. Standards Balloted
None
10. Standards Re-circulated
C37.94 IEEE Standard for N Times 64 Kilobit Per
Second Optical Fiber Interfaces Between Teleprotection
and Multiplexer Equipment
C37.104 IEEE
Guide for Automatic Reclosing of Line Circuit
Breakers for AC Distribution and Transmission Lines
11. Standards to be Re-circulated
PC37.105 IEEE Standard for Qualifying Class 1E Protective Relays and Auxiliaries for Nuclear Power Generating Stations
12. Standards due for 5
year review/to be submitted for Re-affirmation
C37.106 Guide
for Abnormal Frequency Protection for Power Generating Plants
C37.115 Standard
Test Method for Use in the Evaluation of Message Communications Between
Intelligent Electronic Devices in an Integrated Substation Protection, Control
and Data Acquisition System
13.
Standards withdrawn
None
14. New PARs applied for
PC37.98 Standard
Seismic Testing of Relays
15. New PARs
approved
PC37.90.1
Standard Surge Withstand Capability (SWC) Tests for Relays and Relay Systems
Associated with Electric Power Apparatus
PC37.98 Standard
Seismic Testing of Relays
PC37.118 Standard for Synchrophasors
for Power Systems
16. PAR Extensions applied for
None
None
18. Modified PAR approved
None
19. Modified PAR Submitted
PC37.98 Standard
Seismic Testing of Relays
20. PARs Withdrawn
21. PARs expiring at the end of 2008
None
SUBMITTAL DEADLINES & STANDARDS BOARD MEETING SCHEDULE
PAR/Standard Submittal Deadline Standards Board Meeting